Flood control

Flood control is one of the subtopics of Water Resources and Environmental Engineering in the FE Civil exam specification. Questions here are short: one scenario, four choices and about three minutes to answer with the FE Reference Handbook open beside you.

What you can be asked

These are the ideas our problems on Flood control are built around. Each one is covered by at least one problem in the bank.

  • Detention storage volume
  • Reservoir routing continuity
  • Flood frequency / exceedance probability
  • Weir or spillway discharge

Our practice bank has 7 problems on flood control. Every problem is a calculation with a numeric answer. 3 of them come with a diagram. 3 use SI units and 4 use US customary units, as the exam mixes both.

Try one: a free Flood control problem

The solution shows the steps with units, where the equation sits in the Handbook, and the mistake behind each wrong choice.

Free sample SI units

The emergency spillway of a flood-control basin is a level concrete crest 10 m long that behaves as a suppressed rectangular weir (free discharge, no end contractions) with a weir coefficient of 1.84 in SI units. The spillway must pass a design flood of 25 m³/s. The head on the spillway crest at the design flood (m) is most nearly:

  1. A0.826
  2. B1.23
  3. C1.36
  4. D1.58

Work it out first. On the exam you would have about three minutes.

Show the answer and worked solution

AnswerB1.23

Find it in the Handbook

Civil Engineering

Weir Formulas

Weir Formulas, rectangular, free discharge suppressed: , with for SI units

Search (Ctrl+F)

Weir Formulasrectangular weir

Given

  • Design discharge m³/s
  • Crest length m, suppressed rectangular weir, free discharge
  • Weir coefficient (SI)

Find

Head on the crest,

  1. Weir equation solved for the head term

    A suppressed rectangular weir with free discharge follows (with , lengths are in m and in m³/s). Rearranging, .

  2. Head on the crest

    Undo the power by raising both sides to the power: m. Check: m³/s, which matches the design flood to rounding.

Why the other choices are wrong

  • A0.826 m comes from using , the USCS coefficient, with metric values: m. With meters and m³/s the coefficient is 1.84.
  • C1.36 m is , which equals , not . Discharge is not proportional to the head; finish by raising 1.359 to the 2/3 power, which gives 1.23 m.
  • D1.58 m comes from raising 1.359 to the 3/2 power: . Going from back to takes the inverse exponent, 2/3: m.

Exam-day tip

When you solve a weir equation for head, the exponent flips to . Plug your answer back into as a ten-second check.

Practice more Flood control

The bank has 7 problems on this subtopic and 100 across Water Resources and Environmental Engineering. Practice quizzes are part of membership. Not a member yet? The free diagnostic shows which areas to work on first. Through December 31, practice quizzes are free with a free account.

More in Water Resources and Environmental Engineering