Project controls

Project controls is one of the subtopics of Construction Engineering in the FE Civil exam specification. Questions here are short: one scenario, four choices and about three minutes to answer with the FE Reference Handbook open beside you.

What you can be asked

These are the ideas our problems on Project controls are built around. Each one is covered by at least one problem in the bank.

  • Critical path duration
  • Total float
  • Free float
  • Early and late start and finish
  • Activity-on-node network logic
  • PERT expected time and variance
  • Crashing cost slope
  • Earned value: CV and SV
  • CPI and SPI
  • Estimate at completion
  • Resource leveling (simple)
  • Percent complete / S-curve

Our practice bank has 19 problems on project controls. Every problem is a calculation with a numeric answer. 8 of them come with a diagram. 10 use SI units and 9 use US customary units, as the exam mixes both.

Try one: a free Project controls problem

The solution shows the steps with units, where the equation sits in the Handbook, and the mistake behind each wrong choice.

Free sample US customary units

A pump station contract has a budget at completion of $2,400,000. At the latest status date the budgeted cost of work scheduled is $1,100,000, the budgeted cost of work performed is $900,000, and the actual cost of work performed is $1,000,000. Assuming the cost performance to date continues for all remaining work, the estimate at completion ($) is most nearly:

  1. A1,670,000
  2. B2,350,000
  3. C2,500,000
  4. D2,670,000

Work it out first. On the exam you would have about three minutes.

Show the answer and worked solution

AnswerD2,670,000

Find it in the Handbook

Civil Engineering

Forecasting

Estimate at completion, EAC = (ACWP + ETC), with ETC = (BAC − BCWP)/CPI and CPI = BCWP/ACWP

Search (Ctrl+F)

Estimate to completeOriginal project estimate

Given

  • Budget at completion: BAC = 2,400,000 USD
  • Planned value: BCWS = 1,100,000 USD
  • Earned value: BCWP = 900,000 USD
  • Actual cost: ACWP = 1,000,000 USD

Find

Estimate at completion, EAC

  1. Cost performance index

    The cost index compares what the completed work was budgeted to cost with what it actually cost: CPI = BCWP / ACWP = 900,000 / 1,000,000 = 0.900. Each dollar spent has earned only 90 cents of budgeted work. The planned value (BCWS) measures schedule, not cost, and is not needed here.

  2. Estimate to complete

    The work still to be earned is BAC − BCWP = 2,400,000 − 900,000 = 1,500,000 USD at budget rates. If the same cost efficiency continues, it will actually cost ETC = 1,500,000 / 0.900 = 1,667,000 USD.

  3. Estimate at completion

    Add what has already been spent: EAC = ACWP + ETC = 1,000,000 + 1,667,000 = 2,667,000 USD, which rounds to 2,670,000 USD. The project is forecast to overrun its budget by about 267,000 USD.

Why the other choices are wrong

  • A1,670,000 USD is the estimate to complete, (2,400,000 − 900,000)/0.900 = 1,666,667 USD, which is only the cost of the work still to do. The estimate at completion covers the whole job, so add the 1,000,000 USD already spent: EAC = ACWP + ETC = 2,666,667 USD.
  • B2,350,000 USD comes from multiplying the remaining budgeted work by the CPI instead of dividing: 1,000,000 + (1,500,000)(0.900) = 2,350,000 USD. That makes a job that is over budget forecast below its budget. A CPI of 0.900 means each budgeted dollar of work costs more than a dollar, so divide: 1,500,000/0.900 = 1,666,667 USD.
  • C2,500,000 USD adds the remaining work at its original budget to the actual cost, 1,000,000 + 1,500,000, which assumes the rest of the job will run exactly on budget. The stem says the cost performance to date continues, so the remaining 1,500,000 USD of work must be divided by the CPI of 0.900 before it is added.

Exam-day tip

When the CPI is assumed to continue, EAC also equals BAC divided by CPI (2,400,000 / 0.900), a one-line check. A CPI below 1 must give an EAC above the budget.

Practice more Project controls

The bank has 19 problems on this subtopic and 80 across Construction Engineering. Practice quizzes are part of membership. Not a member yet? The free diagnostic shows which areas to work on first. Through December 31, practice quizzes are free with a free account.

More in Construction Engineering