A hydraulic excavator with a 2.5 yd³ bucket (loose measure) digs common earth from a cut. The bucket fill factor is 0.90, the average cycle time is 0.40 min, and the machine does productive work for 50 minutes of each hour. The soil swells 25% when excavated; that is, its loose volume is 25% greater than its bank (in-place) volume. The excavator's production in bank measure (yd³/h) is most nearly:
- A225
- B250
- C281
- D352
Work it out first. On the exam you would have about three minutes.
Show the answer and worked solutionHide the answer and worked solution
AnswerA225
Find it in the Handbook
Civil Engineering
Earthwork formulas
Production = bucket volume × fill factor × (productive min/h ÷ cycle time), then loose to bank by dividing by (1 + swell) (standard method; the Handbook has no formula for it)
Search (Ctrl+F)
Given
- Bucket capacity 2.5 yd³ loose, fill factor
- Cycle time 0.40 min, 50 productive minutes per hour
- Swell 25% (loose volume = 1.25 × bank volume)
Find
Hourly production in bank cubic yards
Loose volume per cycle
The bucket does not come up completely full, so each cycle moves the rated capacity times the fill factor: 2.5 × 0.90 = 2.25 yd³ of loose soil.
Cycles per hour
Only 50 minutes of each hour are productive, so the number of cycles in an hour is 50 / 0.40 = 125. Loose production is 2.25 × 125 = 281.3 yd³/h.
Convert loose to bank measure
Soil expands when dug, so a loose cubic yard holds less soil than a bank cubic yard. With 25% swell, bank volume = loose volume / 1.25: 281.3 / 1.25 = 225 yd³/h of in-place material.
Why the other choices are wrong
- B250 yd³/h comes from treating every bucket as completely full: (2.5)(125)/1.25 = 250. The fill factor of 0.90 says an average bucketful is only 2.5 × 0.90 = 2.25 yd³ loose; use that as the volume per cycle.
- C281 yd³/h is the production in loose measure, (2.25)(125) = 281.25 yd³/h. The question asks for bank measure, and dug soil takes up 25% more room than it did in place, so divide by 1.25 to get 225 yd³/h.
- D352 yd³/h comes from multiplying the loose production by 1.25 instead of dividing: (281.25)(1.25) = 351.6 yd³/h. That would make the in-place volume larger than the loosened volume. Loose = bank × 1.25, so going from loose to bank you divide by 1.25.
Exam-day tip
Decide the direction of the swell conversion before computing: bank volume is always the smaller number, so going from loose to bank you divide by (1 + swell).