Construction estimating

Construction estimating is one of the subtopics of Construction Engineering in the FE Civil exam specification. Questions here are short: one scenario, four choices and about three minutes to answer with the FE Reference Handbook open beside you.

What you can be asked

These are the ideas our problems on Construction estimating are built around. Each one is covered by at least one problem in the bank.

  • Concrete volume takeoff
  • Reinforcing steel weight takeoff
  • Earthwork quantity and cost
  • Unit cost estimate
  • Cost index adjustment
  • Labor and equipment cost for an activity
  • Overhead, profit and markup
  • Masonry or formwork area takeoff
  • Scaling by size (six-tenths rule)
  • Contingency and bid total

Our practice bank has 17 problems on construction estimating. Every problem is a calculation with a numeric answer. 6 of them come with a diagram. 7 use SI units and 10 use US customary units, as the exam mixes both.

Try one: a free Construction estimating problem

The solution shows the steps with units, where the equation sits in the Handbook, and the mistake behind each wrong choice.

Free sample US customary units

A contractor's records show that slab-on-grade concrete cost $480 per cubic yard in place in a year when the construction cost index was 250. The index is now 300. A new rectangular slab-on-grade measures 60 ft by 40 ft in plan and is 6 in. thick. Using the neat concrete volume (no waste allowance) and the unit cost adjusted to the current index, the estimated cost of the new slab ($) is most nearly:

  1. A17,800
  2. B21,300
  3. C25,600
  4. D76,800

Work it out first. On the exam you would have about three minutes.

Show the answer and worked solution

AnswerC25,600

Find it in the Handbook

Chemical Engineering

Cost Indexes

Cost index relation: current cost = (Cost in year M)(Current Index / Index in year M), applied here to a unit cost

Search (Ctrl+F)

Cost IndexesCurrent Index

Given

  • Historical unit cost 480 USD/yd³ in place at index 250; current index 300
  • Slab 60 ft × 40 ft in plan, 6 in. thick
  • Neat volume, no waste

Find

Estimated current cost of the slab

  1. Quantity takeoff

    Convert the thickness to feet (6 in. = 0.5 ft) and multiply out the volume: 60 × 40 × 0.5 = 1200 ft³. There are 27 ft³ in a cubic yard, so the quantity is 1200 / 27 = 44.44 yd³.

  2. Update the unit cost

    A cost index scales a historical cost to today in proportion to the index values: current unit cost = 480 × (300 / 250) = 576 USD/yd³.

  3. Extend quantity by unit cost

    Cost = 44.444 × 576 = 25,600 USD.

Why the other choices are wrong

  • A17,800 USD comes from turning the index ratio upside down: 480 × 250/300 = 400 USD/yd³, and (1200/27)(400) = 17,778 USD. That lowers the price although the index rose. Put the current index on top: 480 × 300/250 = 576 USD/yd³.
  • B21,300 USD is the slab priced at the historical unit cost, (1200/27)(480) = 21,333 USD. That price belongs to a year when the index was 250; multiply it by 300/250 to bring it to today's price level, 576 USD/yd³.
  • D76,800 USD comes from dividing cubic feet by 9 instead of 27: 1200/9 = 133.3, and 133.3 × 576 = 76,800 USD. Nine is the number of square feet in a square yard. A cubic yard is 3 × 3 × 3 = 27 ft³, so the quantity is 1200/27 = 44.44 yd³.

Exam-day tip

Write the index ratio as current over historical. Prices have risen when the index has risen, so the adjusted unit cost must be larger than the old one.

Practice more Construction estimating

The bank has 17 problems on this subtopic and 80 across Construction Engineering. Practice quizzes are part of membership. Not a member yet? The free diagnostic shows which areas to work on first. Through December 31, practice quizzes are free with a free account.

More in Construction Engineering