An aluminum foundry pours pump housings. Its total production cost was $148,000 in a month when it poured 30,000 kg of castings and $184,000 in a month when it poured 45,000 kg. Assume that the total monthly cost is a fixed cost plus a constant variable cost per kilogram poured, and that both months fall in the same operating range. The foundry's fixed cost per month ($) is most nearly:
- A25,300
- B40,000
- C76,000
- D112,000
Work it out first. On the exam you would have about three minutes.
Show the answer and worked solutionHide the answer and worked solution
AnswerC76,000
Find it in the Handbook
Engineering Economics
Breakeven Analysis
Total cost = fixed cost + (variable cost per unit) output, split using two operating points: , (standard method; the Handbook has no formula for it)
Search (Ctrl+F)
Given
- Low month: total cost $148,000 for 30,000 kg poured
- High month: total cost $184,000 for 45,000 kg poured
- Total cost = fixed cost + (variable cost per kg) kg poured
Find
Fixed cost per month
Variable cost per kilogram
Only the variable cost changes between the two months: cost rises by $36,000 while output rises by 15,000 kg, so = $2.40 per kg.
Fixed cost
The low month's variable cost is = $72,000, so = $76,000 per month.
Why the other choices are wrong
- A$25,300 uses the high month's average cost, per kg, as the variable cost: . An average cost still contains the fixed cost; the variable cost is the slope, per kg.
- B$40,000 pairs the low month's cost with the high month's output: . Subtract the variable cost of the same month whose total you start from: .
- D$112,000 pairs the high month's cost with the low month's output: . Use matching values from one month: .
Exam-day tip
When you split a cost into fixed and variable parts, plug the fixed cost back into the other operating point before you answer; if it does not reproduce that month's total, you paired a cost with the wrong quantity.