A soft clay layer 6 m thick lies between two free-draining sand layers and has a coefficient of consolidation of 1.8 m²/yr. A planned warehouse alone would cause an ultimate consolidation settlement of 300 mm. To get this settlement out of the way before construction, a temporary preload fill is placed that would, if left indefinitely, cause an ultimate settlement of 400 mm; the fill is removed once the clay has settled 300 mm. The time factors for average degrees of consolidation of 50%, 75% and 90% are 0.197, 0.477 and 0.848. No vertical drains are installed. The time the preload must stay in place (yr) is most nearly:
Swipe the diagram sideways to see all of it.
- A0.795
- B2.39
- C4.24
- D9.54
Work it out first. On the exam you would have about three minutes.
Show the answer and worked solutionHide the answer and worked solution
AnswerB2.39
Find it in the Handbook
Civil Engineering
Variation of time factor with degree of consolidation
Approximate settlement and time factor , with at U = 75% (Variation of time factor with degree of consolidation)
Search (Ctrl+F)
Given
- Clay thickness m, sand above and below (two-way drainage), m²/yr
- Target settlement 300 mm; ultimate settlement under the preload 400 mm
- , , at , ,
Find
Time for the clay to settle 300 mm under the preload
Degree of consolidation needed under the preload
While the fill is in place the clay is heading for the preload's ultimate settlement of 400 mm, and settlement at any time is the average degree of consolidation times that ultimate value. The fill can come off when , that is 75%. The matching time factor is . This is the benefit of a surcharge: only 75% consolidation is needed instead of nearly 100%.
Drainage path
Water can leave the clay through the sand at both its top and its bottom, so the longest distance a drop of water travels is half the layer thickness: m.
Time required
From the definition of the time factor, , so yr, or about 2.39 yr.
Why the other choices are wrong
- A0.795 yr comes from leaving the drainage path unsquared: , which does not even have units of time. The time factor is , so yr.
- C4.24 yr comes from using the time factor for 90% consolidation: yr. Under the preload the target of 300 mm is only of the ultimate settlement, so use .
- D9.54 yr comes from using the full 6 m thickness as the drainage path: yr. That applies only when one boundary is impervious. With sand above and below, water drains both ways and m.
Exam-day tip
Two checks on every consolidation-time problem: the drainage path is half the thickness only when both boundaries drain, and it is squared.