Skip to content

Free in December. Through December 31, every feature for every exam is free with a free account. No plan, no card.

Free through December 31. Every feature for every exam, free with an account. No plan, no card. Create a free account

Free through December 31. Your account has every feature for every exam until then.

Soil stabilization

Soil stabilization is one of the subtopics of Geotechnical Engineering in the FE Civil exam specification. Questions here are short: one scenario, four choices and about three minutes to answer with the FE Reference Handbook open beside you.

What you can be asked

These are the ideas our problems on Soil stabilization are built around. Each one is covered by at least one problem in the bank.

  • Compaction specification and lift (conceptual)
  • Preloading and vertical drains
  • Chemical stabilization or geosynthetics (conceptual)

Our practice bank has 4 problems on soil stabilization. 2 are calculations and 2 are concept questions with no calculation. 2 of them come with a diagram. 1 use SI units and 3 use US customary units, as the exam mixes both.

Try one: a free Soil stabilization problem

The solution shows the steps with units, where the equation sits in the Handbook, and the mistake behind each wrong choice.

Free sample SI units

A soft clay layer 6 m thick lies between two free-draining sand layers and has a coefficient of consolidation of 1.8 m²/yr. A planned warehouse alone would cause an ultimate consolidation settlement of 300 mm. To get this settlement out of the way before construction, a temporary preload fill is placed that would, if left indefinitely, cause an ultimate settlement of 400 mm; the fill is removed once the clay has settled 300 mm. The time factors for average degrees of consolidation of 50%, 75% and 90% are 0.197, 0.477 and 0.848. No vertical drains are installed. The time the preload must stay in place (yr) is most nearly:

Swipe the diagram sideways to see all of it.

Temporary preload fillSand (free-draining)Soft claycv = 1.8 m²/yrSand (free-draining)6 m
  1. A0.795
  2. B2.39
  3. C4.24
  4. D9.54

Work it out first. On the exam you would have about three minutes.

Show the answer and worked solution

AnswerB2.39

Find it in the Handbook

Civil Engineering

Variation of time factor with degree of consolidation

Approximate settlement and time factor , with at U = 75% (Variation of time factor with degree of consolidation)

Search (Ctrl+F)

time factoraverage degree of consolidationTwo-way drainage

Given

  • Clay thickness m, sand above and below (two-way drainage), m²/yr
  • Target settlement 300 mm; ultimate settlement under the preload 400 mm
  • , , at , ,

Find

Time for the clay to settle 300 mm under the preload

  1. Degree of consolidation needed under the preload

    While the fill is in place the clay is heading for the preload's ultimate settlement of 400 mm, and settlement at any time is the average degree of consolidation times that ultimate value. The fill can come off when , that is 75%. The matching time factor is . This is the benefit of a surcharge: only 75% consolidation is needed instead of nearly 100%.

  2. Drainage path

    Water can leave the clay through the sand at both its top and its bottom, so the longest distance a drop of water travels is half the layer thickness: m.

  3. Time required

    From the definition of the time factor, , so yr, or about 2.39 yr.

Why the other choices are wrong

  • A0.795 yr comes from leaving the drainage path unsquared: , which does not even have units of time. The time factor is , so yr.
  • C4.24 yr comes from using the time factor for 90% consolidation: yr. Under the preload the target of 300 mm is only of the ultimate settlement, so use .
  • D9.54 yr comes from using the full 6 m thickness as the drainage path: yr. That applies only when one boundary is impervious. With sand above and below, water drains both ways and m.

Exam-day tip

Two checks on every consolidation-time problem: the drainage path is half the thickness only when both boundaries drain, and it is squared.

Practice more Soil stabilization

The bank has 4 problems on this subtopic and 92 across Geotechnical Engineering. Practice quizzes are part of membership. Not a member yet? The free diagnostic shows which areas to work on first. Through December 31, practice quizzes are free with a free account.

More in Geotechnical Engineering