Uncertainty

Uncertainty is one of the subtopics of Engineering Economics in the FE Civil exam specification. Questions here are short: one scenario, four choices and about three minutes to answer with the FE Reference Handbook open beside you.

What you can be asked

These are the ideas our problems on Uncertainty are built around. Each one is covered by at least one problem in the bank.

  • Expected value of cost
  • Expected value decision between alternatives
  • Risk as probability times consequence
  • Expected annual flood or failure damage
  • Decision tree

Our practice bank has 9 problems on uncertainty. Every problem is a calculation with a numeric answer. 2 of them come with a diagram. 4 use SI units and 5 use US customary units, as the exam mixes both.

Try one: a free Uncertainty problem

The solution shows the steps with units, where the equation sits in the Handbook, and the mistake behind each wrong choice.

Free sample US customary units

A contractor will protect a riverbank excavation with a temporary cofferdam for one construction season. With the standard cofferdam, the probability that a flood overtops it during the season is 0.15. Raising the cofferdam costs an additional $38,000 and lowers the overtopping probability to 0.04. With either cofferdam, an overtopping would cause $420,000 in damage and delay costs, and at most one overtopping is considered. Ignoring the time value of money, the expected net savings from raising the cofferdam ($) is most nearly:

  1. A8,200
  2. B16,800
  3. C25,000
  4. D46,200

Work it out first. On the exam you would have about three minutes.

Show the answer and worked solution

AnswerA8,200

Find it in the Handbook

Engineering Economics

Economic Decision Trees

Expected Value , applied to the cost of each alternative

Search (Ctrl+F)

Economic Decision TreesChance node

Given

  • Overtopping probability, standard cofferdam: 0.15
  • Overtopping probability, raised cofferdam: 0.04
  • Added cost to raise the cofferdam: 38,000 USD (certain)
  • Loss if overtopped: 420,000 USD (either design)

Find

Expected net savings from raising the cofferdam

  1. Expected loss for each design

    The expected value of an uncertain cost is the cost times its probability. Standard cofferdam: 0.15 × 420,000 = 63,000 USD. Raised cofferdam: 0.04 × 420,000 = 16,800 USD.

  2. Reduction in expected loss

    Raising the cofferdam lowers the expected loss by 63,000 - 16,800 = 46,200 USD. Some risk remains, so only the difference counts as a benefit.

  3. Subtract the certain added cost

    The extra 38,000 USD is spent whether or not a flood occurs, so it is subtracted in full: 46,200 - 38,000 = 8,200 USD of expected net savings. The raised cofferdam is the better choice on an expected-value basis.

Why the other choices are wrong

  • B16,800 USD is the expected loss that remains with the raised cofferdam, 0.04 × 420,000. That is a cost still carried, not a saving. The saving is the drop in expected loss, 63,000 - 16,800 = 46,200 USD, less the 38,000 USD spent.
  • C25,000 USD is 63,000 - 38,000, which assumes the raised cofferdam removes the flood risk completely. It still has a 0.04 chance of being overtopped, so its expected loss of 16,800 USD has to be counted: 63,000 - 16,800 - 38,000 = 8,200 USD.
  • D46,200 USD is the reduction in expected loss, 63,000 - 16,800, before paying for the work. The question asks for net savings, so subtract the certain 38,000 USD cost of raising the cofferdam.

Exam-day tip

Write the total expected cost of each alternative (certain cost plus probability times loss) and subtract. Standard: 63,000. Raised: 38,000 + 16,800 = 54,800. The difference, 8,200, falls out with no chance of dropping a term.

Practice more Uncertainty

The bank has 9 problems on this subtopic and 47 across Engineering Economics. Practice quizzes are part of membership. Not a member yet? The free diagnostic shows which areas to work on first. Through December 31, practice quizzes are free with a free account.